Transport, Economy, Environment and Enterprise
Overview and Scrutiny Committee
17 October 2024
NY Highways Performance and Progress
Report of the Corporate Director - Environment
1.0 Purpose of Report
1.1 To provide members with an update on the progress and performance to date of NY Highways (NYH), North Yorkshire Council’s company for the operational delivery of highway services.
|
2.0 Key Background Information
2.1 A highway delivery options exercise was undertaken in 2018/19 to determine the mechanism for the operational delivery of highways services. In April 2019 the Executive approved the implementation of a wholly owned “Teckal company” to deliver the highways operational services. A Teckal company was recommended as the preferred way forward as this would provide greater flexibility for the then North Yorkshire County Council (NYCC). Future years capital budgets were unclear, it was clear that innovation and efficiency needed to be a main driver for a replacement Highway Maintenance Contract. Upon the approval of the Teckal company a 5 Year Plan was developed which contained the following goals:
· 2019/20 and 2020/21 Development of NY Highways (years 1 and 2)
· 2021/22 Implementation of NY Highways (year 3)
· 2022/23 and 2023/24 Review performance of NY Highways (years 4 and 5)
2.2 NY Highways completed Year 5 of the 5 Year Plan during 2023/24 and has continued to undertake collaborative reviews with North Yorkshire Council (NYC) colleagues on current and future ways of working that promote innovation and efficiency throughout its services. This is the latest in a series of annual update reports.
2.3 A number of achievements were recognised in the report to the meeting of the Committee on 10 July 2023 relating to the 2022/23 year, including:
· Budget savings for NYC - £350k of efficiency savings for NYC in revenue activities
· Increase the operational staff base and resilience
· Apprentices (employing) 14+ apprentices within 2022/23
· “Lunch n learn” events continued and are well attended from colleagues and partners
· The Staff restructure was reviewed in December 2022, and changes implemented in January 2023
· ISO accreditation – work to achieve ISO 9001, 14001 & 45001 accreditation
· Review Schedule of Rates (SoRs) to drive out further efficiencies and benchmarking against National Schedule of Rates
· KaarbonTech Gully emptying programme - 85% of the whole cyclic programme was completed in 22/23 – a 10% improvement on the previous year
· Improvements in responses to defects completed within prescribed timescales improved dramatically in 22/23
· Delivery of a high quality effective winter service
· Enhanced working relationship between NYH and NYC staff
· business opportunities being explored
· a significant step towards better integrated and refined financial systems
2.4 In a similar manner,NYH set out a number of initiatives for 2023/24, aimed to add value to its business:
· Increasing workforce resilience (and skills)
· Evolving the Health and Safety Process
· Further improvements to finance systems to provide robust data management
· Develop robust contract procurement management systems (includes DPS)
· Review of inherited fleet
· Identifying opportunities for commercial trading
· Recognising the need for positive end to end Customer Interface
· Working towards the ambition for carbon neutrality and sustainable material use
· Conclude ISO accreditation - ISO 9001, 14001 & 45001 accreditation for the company,
· Continue Apprentice Development
· Further NYC budget savings (revenue)
· Continue to develop staff across the business to reach their full potential.
· Trial innovative and new ways of working
· Review Schedule of Rates (SoRs) - Continue to undertake cost/value reporting to enhance the accuracy of the cost base and drive out further efficiencies.
3.0 Review of 2023/24
3.1 A review of the 2023/24 year has seen NYH achieve a number of significant successes.
3.2 Budget savings for NYC - £1.9m of savings for NYC in revenue activities during 2023/24 was achieved as a consequence of efficiencies and reduced costs of delivery.
3.3 During 2023/24 a total of 24 Apprentices were employed across NY Highways. 15 in the Operations Team, two in Commercial, six in Fleet and one in Street Lighting. Of the 24 Apprentices currently on the programme, 42% completed within quarter one of 2024, with a further 17% expected to complete within the financial year.
Apprenticeship |
Total Number of Apprentices |
Business Area |
Highways Maintenance Skilled Operative (L2) |
14 |
Operations |
Construction Quantity Surveying Tech (L4) |
2 |
Commercial |
Heavy Vehicle Service and Maintenance Tech (L3) |
5 |
Fleet |
Motor Vehicle Service and Maintenance Tech – Light (L3) |
1 |
Fleet |
Civil Engineering Senior Tech (L4) |
1 |
Operations |
Installation and Maintenance Electrician (L3) |
1 |
Operations (Street Lighting) |
3.4 Recruitment of high-quality operational staff continues to be a challenge for the business due to a shortage of construction/highway operatives. NYH is looking to attract employees from other industries and re-train/up-skill them to meet its staffing requirements.
3.5 During 2023/24 there has been an increase in the headcount and FTE to reflect the growth in the business and increased NYC capital and revenue spend. Correspondingly the vacancy rate has reduced. The average age remains static and it is representative of an aging workforce. NYH is aware of this with discussions taking place for how the roles will be filled when current postholders start to look to retire.
3.6 Sickness Absence for the core workforce in 2023/24 is higher overall than the previous year, however days lost per FTE still falls below the reported average of 5.7 days (ONS, April 2023). Short term absence has reduced in Q4 from all other quarters and in comparison to 2022/23, however long-term sickness absence has increased making up 81% of the working days lost. Case management is aiming to bring the figures down in 2024/25. Proactive work including a review of the Attendance Management Policy, regular conversations with managers and staff engagement sessions will target bringing about a reduction in absence.
3.7 The Continued Professional Development (CPD) of staff has remained a constant during 2023/24. A mix of staff, Operations Manager to Operatives attended the Local Council Roads Innovation Group (LCRIG) Innovation Festival where they were able to see new products and techniques, along with meeting a range of suppliers and subcontractors to the industry. This was supplemented by a series of Lunch and Learn sessions which also included colleagues from East Riding, City of York and Kirklees Councils. These sessions included talks on Trenchless pipe repair, Surface retexturing and sustainable kerb solutions and were made available to all. Tarmac’s CPD session relating to sustainable surfacing materials, techniques and equipment was also supplemented with an invite to their mixing plant at Leeds to see first-hand the information presented.
3.8 As per the Business Plan for 2023/24 ISO accreditation was achieved for ISO 9001, 14001 & 45001. Gaining these accreditations was critical in creating more tendering opportunities for NYH within the Teckal operating model rules. Furthermore, having Quality, Health Safety and Environment processes embedded in the way NYH work provides confidence that robust audits and checks are in place that minimise risk.
3.9 Review Schedule of Rates (SoRs) – NYH continue to undertake cost/value analysis and reporting to enhance the accuracy of the cost base and drive out further efficiencies and benchmarking against the National Schedule of Rates is now being used as a comparator. This allows a greater transparency and more accurate means of measuring efficiency as opposed to comparison against outdated inaccurate rates from previous contracts, especially as some rates were loss-leaders where true costs may have been balanced against cost recovery from other more profitable elements of the wider contract.
3.10 Other notable achievements include:
3.10.1 KaarbonTech Gully emptying programme - 93% of the whole cyclic programme was completed in 2023/24 - a further improvement on the previous year figure of 85%. Of those gullies attended, 92% did need cleaning, showing the risk based / data-led programme is effective.
3.10.2 Revenue Maintenance works – response to defects completed within the timescale set on works orders has improved dramatically in the last two years. During the first year of NYH, less than 50% of works orders were completed on time; since then, this figure has improved month on month to a point where now 78% of repairs are completed on (or before) time. Work to further improve this figure continues by restructuring gangs as well as deploying a range of repair techniques coupled with the introduction of expected output levels linked to individual and team appraisal targets. There is also a strong drive on right first time / fix once approach being instilled into the workforce alongside ensuring the most appropriate and cost-effective solution is enacted.
3.10.3 Successful delivery of capital works, including ongoing joint working to improve management of the capital programme.
3.10.4 From an environmental / sustainability initiatives perspective, during 2023/24 as part of our forward capital programme works we undertook preparatory work to incorporate in-situ recycling as part of the 2024/25 highways capital annual programme, with one trial site completed, one underway in mid September 2024 and a further site planned to start in March 2025. In addition, following research in 2023/24, we are trialling some recycled plastic kerbs this current financial year.
3.11 A review of objectives for 2023/24 contained in the NY Highways Business Plan evidences:
· Delivery of another high quality and effective winter service during the 2023/24 season and without significant incidents
· internal client relations have continued to mature culminating in a joint Team Workshop that resulted in the identified continual improvement initiatives to be delivered during 2024/25
· Senior Management appointments were made in the Operations Team and Business Support Teams building on the one team approach by working with senior Managers in NYC.
· Significant progress has been made culminating in more robust integrated and refined financial systems to assist in more effective financial management within NYH to allow more effective budget forecasting certainty in NYC
· A detailed review of the current vehicle fleet commenced. It is anticipated new vehicles will start to be procured during 2024/25. This is part of an overall rolling replacement programme.
· £1.9M of revenue savings in addition to the shareholder value detailed below.
· Developing the core skills of the workforce to deliver more works internally.
· Shareholder value figures met expectations for 2023/24 as shown below
Shareholder Value |
|
Financial Year: |
2023-24 |
Value |
£000 |
Profit/ (Loss) before Tax |
113 |
NYC Support Service Contracts |
1,430 |
NYC Loan Financing Interest |
1,235 |
Total |
2,778 |
4.0 Health and Safety
4.1 Health and Safety remains of paramount importance to NY Highways. The table below shows that performance figures for 2023/24 were positive, with an improvement on previous years. To drive these continual improvements and maintain focus, more challenging targets were implemented for some key measures during 2023/24. The 2023/24 targets are shown in the table below with the 2022/23 targets in brackets for reference. Targeted campaigns were introduced to improve safety. For example, particular focus was being placed on Driving at Work, Stress and Preparedness for ISO Accreditation.
Safety |
2023/24 Target |
2023 Year end figures |
Accident Frequency Rate |
0.25 (0.25) |
0.17 |
RIDDORS |
<15 (< 15) |
0 |
Days lost to personal injury accidents |
<170 (<350) |
25 |
% of Inspections and Audits without a non-conformity |
>90% (>85%) |
94% |
% of Risk Assessment Reviewed |
100% (>90%) |
100% |
Number of missed Occupational health monitoring appointments |
<5 (<5) |
0 |
Number of Health & Safety campaigns |
4 (4) |
4 |
5.0 Forward Look 2024/25
5.1 The 2024/25 NYH Business Plan describes the future aspirations of the company, some of the key points being:
· Providing value to the Shareholder.
· Achieving an External works profit of greater than £100,000.
· Securing works from other public bodies or delivering revenue generating business from another local authority
· Development of an NPORS certified Training Centre
· Delivery of section 38 and 278 agreement works through Highway Development Services (HDS) allowing HDS to achieve a profit through NYH of greater than £50K
· MOT Test Centre and Increased Fleet offering internally and externally
· Maintain Compliance to ISO standards
· Achieve above 85% of defects fixed within Priority
· Delivery of Capital Works
· Achieve greater than 90% of cyclical gully programme
· Returning greater than £800k of efficiencies back through NSR performance on capital schemes
· Reduce the carbon footprint spend per £1 of turnover. Work on this continues, with an assessment of 2023/24 showing an improvement with a Carbon intensity value kgCO2e/£ of 0.033 compared with 0.039 in the previous year (2022/23)
· Ongoing review of pricing structure for works including refinement of cost value comparison and evaluating all rates from a first principal basis, benchmarked against National Schedule of Rates
· Following completion of a detailed review of the current vehicle it is anticipated new vehicles will start to be procured during Quarter 4 of 2024/25. This is part of an overall rolling replacement programme.
· Senior Leadership Team depot visits have been introduced to keep workforce engaged in the NYH ‘you said / we did’ Strategy. In addition, specific Operative Forums have commenced, initially focused on Gully emptying and Depot Management. These will allow the sharing of best practice, remove inefficiency, and help in identifying and addressing barriers to effective service delivery.
6.0 Alternative Options Considered
6.1 As per para 2.1, the Teckal delivery model was approved as the preferred way forward for delivery of the highways service, therefore no alternative options have been considered as part of this report.
7.0 Financial Implications
7.1 There are no financial implications arising directly as a result of this report as it provides an update on progress. One of the founding principles of the Teckal approach was, through closer working with the Council, to deliver more for the same money or the same for less money. As part of this philosophy, the range of options considered on an operational level is being continually evaluated and evolved in order to ensure maximum efficiency and value for money in how things are delivered on the ground (pothole repair techniques, for example).
7.2 Revised rates and unit costs are being compared with the National Schedule of Rates for such works in order to evidence value for money as part of a suite of tangible metrics to be further developed through 2024/25. In 2023/24, the council was credited £1.9m from NY Highways which was generated through cost reductions and efficiencies and enabled the Council to offset pressures within the highways revenue budget and achieve the savings included within the 23/24 budget.
7.3 Work is currently being undertaken to comprehensively capture both cashable and non-cashable savings in order to fully evidence the benefit of this truly collaborative approach.
8.0 Legal Implications
8.1 NYH is a “Teckal company” which means it is able to trade with the Council, without the Council needing to go through a procurement exercise, as well as external customers. NYH meets all of the Procurement Regulations test for Teckal Exemption.
9.0 Equalities Implications
9.1 An initial equalities impact assessment form was completed and is included as Appendix A. The assessment of this report concluded that there is no impact on people with protected characteristics.
10.0 Climate Change Implications
10.1 A Climate Change Impact Assessment has been undertaken and is included as Appendix B.
11.0 Conclusion
11.1 During the fifth year of operation (2023/24) NYH continued on the improvement journey meeting all substantial targets set in the Business Plan. Continual improvement can be evidenced in the core operational areas of Winter Maintenance, Management of Surface Water (gully emptying) and providing timely repairs to defects and delivery of the capital works programme.
11.2 The core services are at the heart of the Teckal model and will continue to remain a focus. It is also anticipated that during 2024/25 there will be increased non-highways / External works. To help deliver shareholder value and is aligned to the Teckal model. Delivery will be managed alongside maintaining the core services. To avoid a conflict, a dedicated team are being recruited to deliver this workload, thus mitigating any impact on core services. NYH will be continuing to provide the service that North Yorkshire requires to keep the highway network safe and fit for purpose. This will be done through robust processes that demonstrate the value of the Teckal arrangement over other procurement routes.
11.3 NYH will continue to focus on effective and efficient service delivery, strong financial reporting, forecasting and budget control. In addition, NYH will build and develop a workforce that is fit for the future, using its Teckal position to deliver best in value for North Yorkshire Council and in a wider trading environment. NYH in 2024/25 will have delivered works for NYC Property, NYC Parking, NYC bereavement services, NYC Highway Development Services, NYNet, and have tendered for a number of external commercial works. NYH continues to offer NYC significant efficiencies in delivery through a Teckal model.
11.4 NY Highways (NYH) remains committed to making a meaningful, positive impact on local communities by contributing to resilience, safety, sustainable economic growth as well as respecting and enhancing the environment.
12.0 Recommendation
12.1 Members are requested to note the information within the report and offer comments or suggestions where necessary. |
APPENDICES:
Appendix A – Equalities Impact Screening Form
Appendix B – Climate Change Impact Assessment
Karl Battersby
Corporate Director – Environment
County Hall
Northallerton
30 September 2024
Authors:
- Nigel Smith, Head of Highway Operations NYC
- Barrie Mason, Assistant Director - Highways and Transportation, Parking Services, Street Scene, Parks and Grounds
- Jamie Crumlish, Managing Director - NY Highways
- Brian Stanforth, Head of Operations NY Highways
Background Papers – Scrutiny Committee report of 10 July 2023 and 11 July 2022
For further information please contact the author of the report
Initial equality impact assessment screening form
This form records an equality screening process to determine the relevance of equality to a proposal, and a decision whether or not a full EIA would be appropriate or proportionate.
|
|||||||
Directorate |
Environment |
||||||
Service area |
Highways and Transportation, Parking Services, Street Scene Parks and Grounds – Highway Operations |
||||||
Proposal being screened |
Annual report on the progress and performance of NY Highways
|
||||||
Officer(s) carrying out screening |
Nigel Smith – Head of Highway Operations NYC |
||||||
What are you proposing to do? |
To provide members with an update on the progress and performance to date of NY Highways, the Council’s company for the operational delivery of highway services.
|
||||||
Why are you proposing this? What are the desired outcomes? |
This report is an update for members on the progress of NYHighways for the 2023/24 financial year. There are no outcomes other than ensuring that members are aware of how the Teckal company has performed during the past financial year.
|
||||||
Does the proposal involve a significant commitment or removal of resources? Please give details. |
No
|
||||||
Impact on people with any of the following protected characteristics as defined by the Equality Act 2010, or NYCC’s additional agreed characteristics. As part of this assessment, please consider the following questions: · To what extent is this service used by particular groups of people with protected characteristics? · Does the proposal relate to functions that previous consultation has identified as important? · Do different groups have different needs or experiences in the area the proposal relates to?
If for any characteristic it is considered that there is likely to be an adverse impact or you have ticked ‘Don’t know/no info available’, then a full EIA should be carried out where this is proportionate. You are advised to speak to your Equality rep for advice if you are in any doubt.
|
|||||||
Protected characteristic |
Potential for adverse impact |
Don’t know/No info available |
|||||
Yes |
No |
||||||
Age |
|
ü |
|
||||
Disability |
|
ü |
|
||||
Sex |
|
ü |
|
||||
Race |
|
ü |
|
||||
Sexual orientation |
|
ü |
|
||||
Gender reassignment |
|
ü |
|
||||
Religion or belief |
|
ü |
|
||||
Pregnancy or maternity |
|
ü |
|
||||
Marriage or civil partnership |
|
ü |
|
||||
NYC additional characteristics |
|||||||
People in rural areas |
|
ü |
|
||||
People on a low income |
|
ü |
|
||||
Carer (unpaid family or friend) |
|
ü |
|
||||
Does the proposal relate to an area where there are known inequalities/probable impacts (e.g. disabled people’s access to public transport)? Please give details. |
This is a Members’ report on the performance of NYHighways. There are no proposals that would impact on people with protected characteristics.
|
||||||
Will the proposal have a significant effect on how other organisations operate? (e.g. partners, funding criteria, etc.). Do any of these organisations support people with protected characteristics? Please explain why you have reached this conclusion. |
No |
||||||
Decision (Please tick one option) |
EIA not relevant or proportionate: |
Yes |
Continue to full EIA: |
No |
|||
Reason for decision |
This is a report for information only. There are no adverse impact on any of the protected characteristics.
|
||||||
Signed (Assistant Director or equivalent) |
Barrie Mason
|
||||||
Date |
3 October 2024
|
||||||
Climate change impact assessment
The purpose of this assessment is to help us understand the likely impacts of our decisions on the environment of North Yorkshire and on our aspiration to achieve net carbon neutrality by 2030, or as close to that date as possible. The intention is to mitigate negative effects and identify projects which will have positive effects.
This document should be completed in consultation with the supporting guidance. The final document will be published as part of the decision making process and should be written in Plain English.
If you have any additional queries which are not covered by the guidance please email climatechange@northyorks.gov.uk
Version 2: amended 11 August 2021
Title of proposal |
Annual report on the progress and performance of NY Highways
|
Brief description of proposal |
To provide members with an update on the progress and performance to date of NY Highways, the County Council’s company for the operational delivery of highway services.
|
Directorate |
Environment
|
Service area |
Highways and Transportation, Parking Services, Street Scene Parks and Grounds – Highway Operations |
Lead officer |
Nigel Smith – Head of Highway Operations NYC |
Names and roles of other people involved in carrying out the impact assessment |
Barrie Mason - Highways and Transportation, Parking Services, Street Scene Parks and Grounds – Highway Operations |
Date impact assessment started |
20 September 2024 |
Options appraisal Were any other options considered in trying to achieve the aim of this project? If so, please give brief details and explain why alternative options were not progressed.
The teckal delivery model was approved as the preferred way forward for delivery of the highways service, therefore no alternative options have been considered as part of this report
|
What impact will this proposal have on council budgets? Will it be cost neutral, have increased cost or reduce costs?
Please explain briefly why this will be the result, detailing estimated savings or costs where this is possible.
As part of this preferred delivery model, it was acknowledged this would provide greater flexibility for the (then) NYC. Innovation and efficiency, alongside an ongoing challenge to reduce unit cost and deliver as much for the same budget or the same for less budget are an integral part of the operating model. Efficiencies and savings have been outlined in detail in the main body of this report
|
How will this proposal impact on the environment?
|
Positive impact (Place a X in the box below where relevant) |
No impact (Place a X in the box below where relevant) |
Negative impact (Place a X in the box below where relevant) |
Explain why will it have this effect and over what timescale?
Where possible/relevant please include: · Changes over and above business as usual · Evidence or measurement of effect · Figures for CO2e · Links to relevant documents |
Explain how you plan to mitigate any negative impacts.
|
Explain how you plan to improve any positive outcomes as far as possible. |
|
Minimise greenhouse gas emissions e.g. reducing emissions from travel, increasing energy efficiencies etc.
|
Emissions from travel |
√ |
|
|
More effective scheduling and minimising travel distance during winter service and routine maintenance works journey planning |
Ongoing procurement and replacement of fleet will also assist in minimising emissions |
Sharing best practice across NY Highways and NYC |
Emissions from construction |
√ |
|
|
Use of warm mix as opposed to cold mix materials in road and footway repairs. |
Early partnership meetings to reduce / reuse / recycle will assist alongside working to NYC carbon reduction ambition |
Use of NYH carbon counting tool when fully developed will identify areas for improvement /focus |
|
Emissions from running of buildings |
|
|
|
N/A |
|
|
|
Emissions from data storage |
|
|
|
N/A |
|
|
|
Other |
|
√ |
|
|
|
|
|
Minimise waste: Reduce, reuse, recycle and compost e.g. reducing use of single use plastic |
√ |
|
|
|
Early partnership meetings to reduce / reuse / recycle will assist alongside working to NYC carbon reduction ambition |
|
|
Reduce water consumption |
|
|
|
N/A |
|
|
|
Minimise pollution (including air, land, water, light and noise)
|
√ |
|
|
More efficient scheduling of works will reduce overall miles travelled on highway network and therefore minimise air and noise pollution emanating from travelling vehicles |
|
|
|
Ensure resilience to the effects of climate change e.g. reducing flood risk, mitigating effects of drier, hotter summers |
|
|
|
Some schemes delivered by NYH, such as drainage works, will reduce the risk of flooding on the highway network. The risk-based gully cleansing model identifies those parts of the drainage system requiring attendance |
|
The gully schedule is updated on an evolving intelligence/data-led approach |
|
Enhance conservation and wildlife
|
√ |
|
|
Work commenced in 2023/24 and continues into the current financial year to review our grass cutting policy - this includes consideration of biodiversity & how we can enhance highway verges as a natural habitat whilst remaining cognisant of the need for this to not compromise highway safety. NYC and NY Highways are working together to finalise this policy and undertaking a procurement exercise for a new grass cutting contract commencing 01/04/2025
|
|
|
|
Safeguard the distinctive characteristics, features and special qualities of North Yorkshire’s landscape
|
√ |
|
|
Material choice in maintenance and improvement schemes wherever possible reflect the nature of the surrounding environment |
|
|
|
Other (please state below)
|
|
|
|
N/A |
|
|
Are there any recognised good practice environmental standards in relation to this proposal? If so, please detail how this proposal meets those standards. |
NY Highways has appointed and Environmental Consultant to assist with ISO accreditation, however this will also bring benefit in a wider sense (for example, guidance is currently being sought around proposed EA changes waste licences in 2024).
Close working across the delivery partnership from scheme inception stage also allows access to good practice from other organisations, such as wsp, who are a well-established global consultant with a well-established record of environmental good practice
|
Summary Summarise the findings of your impact assessment, including impacts, the recommendation in relation to addressing impacts, including any legal advice, and next steps. This summary should be used as part of the report to the decision maker.
The former North Yorkshire County Council (now North Yorkshire Council) has brought its highways services back in-house through the teckal company, NY Highways Ltd.
NY Highways has a duty and a corporate responsibility to develop and deliver a Carbon Plan to align with the commitment made by the Council where they committed to achieve net carbon neutrality by 2030, or as near to that date as possible.
NY Highways also has a Carbon Management Plan applicable to all operations undertaken by NY Highways and its supply chain. The CMP encompasses:
Continual review and challenge will be key to success and the carbon management tool remains an integral part of ensuring that climate change remains at the forefront of people’s thoughts from scheme inception to completion and in every other area of the business / service delivery |
Sign off section
This climate change impact assessment was completed by:
Authorised by relevant Assistant Director (signature): Barrie Mason
Date: 3 October 2024 |